Another leak

Hooray!

Thursday morning and DH surprises me by telling me that he is going to move all his tools and toolboxes, bicycles and gardening equipment into the bodega, (about time, I hear you say. No? It must just be me then?). This will mean that we can finally use the front entrance to our house, without tripping over ourselves and all the 'stuff' that has accumulated in the porch/passageway these last few months.


The terrace extension.
Nonetheless, my happiness is extremely short-lived as it appears that the terrace is still leaking. Same place as last time, where we extended it to be precise. Not only that, but the tiles have cracked as well. It's just too hot there, even with the dappled shade from the palm tree. 

Fan-bloody-tastic!

Yet another set-back and a new dilemma, namely what on earth shall we use for the floor covering now? After all, it is only half of the terrace that has to be altered; rather than try and match the ceramic tiles that are already in position, we rack our brains trying to decide on a contrasting material, in the hope of making a 'patched-up job' look like a 'design feature' A whitish ceramic tile perhaps? Decking? Shingle? Maybe even some kind of fake grass? None of which 'float my boat'. Dark grey pebbles are a possibility though.

So, on Thursday and Friday, the builders set about lifting the tiles off the offending area, for a third time. They re-enforced the floor again with zinc sheets and yet even more cement. 

Meanwhile DH went in search of roughly 12 square metres of 'piedras de bolas', ball stones. The labourers that he took to help him, were all in favour of digging the pebbles up from the river-bed, as is so often done here in CR. However, DH chose what he thought would be an easiest solution and decided to buy the rocks instead. 

Scattered sacks of 'ball stones'.
On arriving at the stone-works though, DH had the choice of either a digger emptying boulders into the pick-up (BOULDERS not stones mind-you, which would mean us breaking them into smaller pieces) or hand-pick the pebbles himself, load  into sacks and then onto the truck. Hmm, decisions, decisions! So back breaking work ensued, picking over and loading individual pebbles , all 12 sacks of them - a bargain price though as only $30 for the whole lot!

Next week, the fun begins when we ask the builders to lay the pebbles into the concrete evenly. Should be entertaining. I'll report back on their progress!






Thursday 13 March 2014

Making a Laundry Room.

Everyone needs somewhere to do their laundry right? 

A place where the washing machine can be stored. Somewhere to house the hoover (sorry, vacuum cleaner for my non-British friends), the broom, the mop, the bucket, the ironing board, and all the paraphernalia that is associated with housekeeping. And as I love housework so much (not), I prefer to keep these items hidden from view, along with my ironing pile so that I can't see it spilling over the top of the basket, or hear  it gently whispering that it needs doing! 

Having said that, this little area has always been my domain in our house, and had to be included in both the planning and construction of the two major house renovations we undertook back in Blighty. Similarly, the first place that we lived together, a little cottage in the sticks, had its own laundry room: attached to the back wall of the kitchen, you had to access it from the outside - not much fun in the winter, I can tell you. Even here in Costa Rica, when we first arrived and were looking at properties to rent, the kids always joked when seeing the laundry rooms  "Oh look, that's Mum's room". (DH, quite wisely, is not brave enough to say such a thing!). You may tut-tut at the sexist jokes that amuse my boys, as do I, but it does actually mean that I have my very own private space, right in the middle of the house. A spot that I can call my own and that I can go to and hide from arguing kids and grumpy men. A zone, albeit a small and possibly invisible one, where nobody ever manages to find me! I'm assuming such a space is a dream place for most women and/or mothers because in Mallorca, where we had a large, communal laundry room shared by a number of apartments, it didn't matter what time of day or night you ventured down there, you nearly always found some mum or other hiding from their family on the pretence of doing the laundry!

The Before and After shot, but the wrong way round!

Anyway, here at La Casita, the plumbing for the washing machine, along with more than adequate lighting, was already installed in the hallway inglenook, so it made complete sense to utilise the area and turn it into a laundry room. I mean why make more work for yourself by moving all the fixtures when all that's needed is a little imagination? But being in the hallway, close to the front door, the problem was how to hide the proposed laundry area from view. A decorative curtain, beaded or made with shells that we have found on the beach perhaps? Most likely too much hassle, as the strands would be forever getting in the way whilst trying to load the clothes into the washing machine. Bi-fold doors even? No, all the products we found in the various DIY shops were far too flimsy for a rental property. So wooden sliding doors were the sensible option, not necessarily my favourite choice, but ideal for the space.

With no windows in the alcove, we decided on louvered doors, which would allow the air to circulate, preventing any horrid smells that may arise from lingering, damp washing. Three pine doors were purchased along with the runners to make the sliding frame. DH, happy to have a project, set to work rubbing down. As we didn't want to make the hallway too dark and dingy, but still wanted them to contrast with the white of the interior walls, we decided on the 'weathered' look. So as to avoid any runs or paint brush marks, DH, keen to use his paint gun and compressor again, sprayed all three doors with a white paint-wash (a mix of 50:50 paint to water). Me, as a finished product, I would have liked them left a little rough around the edges, but DH is not so inclined and sprayed a final layer of sealer on top - "makes them easier to clean", so he says - and thankfully they still look matt and not shiny.

A hidden laundry space. 
Next, a small false wall had to be built from the ceiling down, so that the top runners had something to attach too. The builders did this for us and then set to hanging the doors: firstly one of them was hung upside down, so it didn't match the other two, and then the wrong way round! Another small detail to test us!

Hey-ho, not to worry, Pura Vida etc., etc.! They are finally hung correctly and look (and of course feel) pretty smooth - nice work DH. 

Now all we need to do is put up some shelves and then furnish it with exciting things like a washing machine. 

Yippee! Can't wait!!


Wednesday 12 March 2014

Joining the world of bloglovin!

<a href="http://www.bloglovin.com/blog/11934005/?claim=ugfpxd87uhh">Follow my blog with Bloglovin</a>

Sunday 2 March 2014

Snagging List Summary.

From this ...

... to this.





When we first started this project, Jose and his team predicted that they would be finished by December, and to be honest, the speed with which they first started working, we thought that they may well be! Then the problems with Napoleon took hold and kind of destroyed the rhythm. The kitchen delayed things and other problems cropped up that just have taken an age to be fixed.
We have now into the month of March and I think we have been working on the snagging list since half-way through January! Builders and constructors Jose and his team may be, but finishers and detailers they are not. I think that they will be just as pleased to finish this job as we will to see them go. 
So for a roundup of February:


The Complete:

  • Air-con is in and boy, it works well. One in each of the bedrooms and one in the kitchen. Nice and cool. 
  • Pool appears to have had no more leaks for a week. Hopefully that is that problem solved. 
  • The awful stench that appears between 2.00 pm and 3.00 pm each day, (the one that I have failed to blog about as no words can describe the fetid odour), has been fixed: not only have we had the cesspit cleaned out, but new pipes installed and so-on at the end of last week. The result, no foul smell when the sun hits the front of the casita mid-afternoon. Only taken two months to sort out that little dilemma!!


The Not-So Complete:

  • Leak from terrace into bodega below ... still needs a little more work!
  • A complication with the front door. For security purposes, it does not work properly, so we need to re-think and re-hang. 
  • Not happy with his worktops in the kitchen, DH has decided to rub them down again and apply another layer of stain. 

Looking back over the photos though at least you can see the progress that has been made. One day, I am sure we will say it has all been worthwhile. 

But for now, we have both had enough and are unable to believe that it will be finished soon!

And from this ...

...to that.